heading

Start Date 23rd July 2007
Current Progress Completed
Fund 455 million US$
(Loan from China)
300 million @ 2% interest
155 million @ 6% interest
GOSL Contribution Rs. 5300 million
Background Capacity 300MW
Norochcholai Coal Power Plant was envisaged to be commissioned in late 1980’s, but due to pressure from various organizations was kept on held. However, His Excellency the President Mahinda Rajapaksha decided to go ahead with the implementation and negotiations started in 2005 and the Contract was signed in 2006
To meet the increasing demand of electricity in the country, and to diversify the power generation mix a major coal plant of 900 MW has been implemented in Norochchole. The Phase I of the project with the capacity of 300 MW was commissioned March 2010 and the Phase II with capacity of 2X300 MW is under implementation. The first 300 MW of Phase II is scheduled to commission in October 2013 and the second 300 MW Phase II will be available from May 2014. The phase I and phase II of the project has been funded by a soft loan of 891 Million USD provided by EXIM Bank of China.

The first stage of this Coal Power station inaugurated by the President cost $ 455 Million, while the second stage is estimated to cost $ 891 Million. The Ministry of Powrr and  energy stated that the funding for this project was provided by the Chinese Government on a long term low interest rate to the Sri Lankan Government. The Construction work is carried out by CMEC while the funding is provided by the EXIM Bank of the Republic of China. As local investment the Sri Lankan Government has invested Rs. 5300 Million for the first stage and Rs. 11,000 Million for the second stage of construction.

A mother ship approximately 5 km at sea transports the coal to the jetty. While each ship has the capacity to bring in 65,000 Metric Tons of coal, 114 Metric tons of coal is needed per hour for a 300 MW power plant. A environmentally friendly Coal storage facility has been constructed with storage capacity for 3 months.

The boiler which is 69M high and 40 M in bredth is heated to a very high temperature, while the steam produced is sent through High preasure and high temperature through turbines, thus producing electricity. In the first stage it travels from the control centre to Veyqangoda which is 117 KM releasing 220 KW to the High power transmitting channel.

This Coal Power station 12 KM from the Palavi junction in the Kalpitiya pensula in the village of Narakkalli was inaugurated by the President in 2006. This Coal power station produces 300 MW in the first stage while 600 MW is produced in the 2nd stage.

For 80 families that lost their property during the 1st stage of construction, houses have been constructed and presented on 20 perches complete with drinking water electricity and all basic facilities, while fishing gear has also been provided for the fisher fork.

The Ministry of Power and Energy stated that with the construction of this Coal Power station the goal of 100% electricity for all will no doubt will be realised.

thum2 thum1